Critical Bridges Update

CCC Logo 4

In addition to the Critical Infrastructure and Major Projects report, this update now also includes information on our much wider programme of Bridge Repairs and Winter Resilience measures.

The Bridge Repair Programme has seen us working on site since the end of August, and is planned to be complete by the end of October with our teams repairing a total of 81 bridges.

The Winter Resilience programme is starting now and will involve implementing defensive measures at a further 18 bridges. While these measures will not make these bridges immune to damage over the coming winter, it will help make them as resilient as possible. Winter Resilience programme includes the building of scour protection and placing rock armour around bridge piers.